This is practical record-keeping guidance, not a design method or a statement of compliance with AS 2159 or Practice Note 28. Follow the project engineer’s specification and equipment manufacturer’s instructions.
This guide covers the practical side: getting a clean final reading, converting pressure to torque, units, and keeping supporting evidence. For what reviewers look for across the whole report, see what engineers and certifiers check in a screw pile installation report.
Two ways crews measure torque
Torque monitors and loggers
Some torque monitors use a load cell to measure torque at the drive output. Depending on the equipment, a monitor may display live readings and save a log or export for each pile. Check the manufacturer’s instructions for what your device measures and records.
Hydraulic pressure gauges
Some crews estimate torque from hydraulic pressure using the drive head manufacturer’s chart or formula. Pressure is not a direct torque measurement. Confirm that the pressure reading, sensor location and conversion suit the exact equipment and operating mode, and that the project engineer accepts the method.
When to take the final reading
Confirm the measurement interval and reporting method before installation. A reading at the instant the pile stops may not represent torque over the specified interval.
Practice Note 28, Version 1 (October 2015), section 6.5, lists “Measurements taken over the last metre of installation or 3D (whichever is the greater)” among the conditions for relying on torque measurements. Its acronym list defines D as helix diameter. This is New Zealand good-practice guidance, not an Australian standard or an automatic acceptance rule for your project. Read Practice Note 28.
That passage does not specify an averaging calculation or sampling frequency. Ask the project engineer which interval, sampling method and reported value to use, including which helix diameter applies to a multi-helix pile. Record any additional depth-by-depth readings required by the project.
In practice:
- Follow the specified installation rate and equipment instructions.
- Observe and record readings over the required interval, rather than relying on a single glance.
- Label the reported value as average, minimum, peak or another specified measure, and record the interval and method used.
- Keep peaks, stalls, obstructions and interruptions in the record. Do not substitute an isolated spike for the specified final-interval value or discard it from the supporting evidence.
Converting pressure to torque
If you are reading a pressure gauge, the conversion depends on the drive head. Use the manufacturer’s chart, table or formula for that model and operating mode. There is no universal PSI-to-Nm conversion.
- Use the figures for the exact drive head model fitted on the day. Record equipment changes. A two-speed head may have different torque figures for each mode.
- Confirm the required measurement points and whether the chart uses differential pressure: supply pressure at the drive minus return pressure. Do not assume a pump gauge reading equals the pressure available across the drive.
- Record the pressure, units, chart reference, operating mode and estimated torque so the engineer can check the basis.
- Name the drive head in the report header.
Digga’s pressure differential gauge guidance describes measuring supply and return pressure at the drive and using a supplied torque chart. Its SD95 product information cautions that output torque specifications are theoretical and depend on system efficiencies. Check the instructions for your equipment rather than treating a chart estimate as a direct measurement.
Crews type torque and pressure readings into Pile Logix by hand as each pile goes in. The installation report records machine PSI and torque in Nm for each pile. See the Pile Logix installation report for the full layout.
Get the units right
Missing or mixed units are one of the easiest ways to have a report questioned.
- Torque: Nm or kNm. 1 kNm = 1,000 Nm. Some imported equipment reads in ft-lb (1 ft-lb ≈ 1.356 Nm).
- Pressure: PSI or bar. 1 bar ≈ 14.5 PSI.
- Pick one unit for each column and stick with it for the whole job.
- If your gauge or logger reads in a different unit to the report, convert once, carefully, and note the original reading if there's any doubt.
Keep the logger's records as supporting evidence
If you use a torque logger, its own records are useful evidence alongside the installation report. Pile Logix does not connect to or import from torque loggers, so treat the two as separate records that should agree:
- Save the logger's export (PDF, CSV or raw data file) for each job, or take a screenshot of the reading at final depth.
- Use the same pile IDs in the logger and in the report, matching the plan.
- Check the figure typed into the report against the logger before you sign off.
- Send the export or screenshots with the report if the engineer wants them.
For pressure gauges, a safely taken photo can support the written reading. Label it with the pile ID and depth. A single photo does not establish torque over an interval or replace a required installation profile.
Calibration
Practice Note 28, section 9.1, recommends calibration of installation equipment and torque measuring devices at least every six months. It also recommends using the same power-head throughout a project where feasible so measured torque can be compared between piles. These are recommendations in that New Zealand guidance, not a universal Australian calibration rule.
Confirm the calibration and verification schedule with the equipment manufacturer and project engineer. Do not use the six-month recommendation to extend a shorter required interval.
- Keep applicable calibration certificates and verification records for the equipment used. Check that they identify the relevant device or assembly.
- Record which machine and drive head were used on each job.
- If a gauge is damaged or reads oddly, stop and check it before carrying on.
Common mistakes
- Recording peak torque from an obstruction instead of the final interval reading.
- Using the conversion chart for a different drive head.
- Writing "8" with no unit, or mixing Nm and kNm in the same column.
- Recording pressure without the drive head, so it can't be converted.
- Filling in readings from memory at the end of the day.
- Pile IDs in the logger that don't match the plan or the report.
- Out-of-date calibration certificates.
Quick checklist
- Engineer's torque requirement and measurement interval confirmed
- Drive head model and its pressure-to-torque figures on hand
- Calibration certificates current
- Final torque recorded for every pile, with units
- Pressure recorded alongside torque where it was converted
- Obstructions, spikes and refusals noted in comments
- Logger export or screenshots saved with matching pile IDs
- Report figures checked against the logger before sign-off
FAQ
Should I record peak torque or average torque?
Record the measure and interval specified by the project engineer. The cited PN28 final-interval passage does not prescribe a peak-versus-average calculation. Do not relabel a peak as an average. Keep peak readings and unusual events as supporting information; a final-interval value does not replace checks on maximum installation torque limits.
Can I just record the hydraulic pressure?
Confirm the required record with the project engineer. PN28 section 9.2 lists a profile of installation torque or pressure with depth. If pressure is used to estimate torque, also record the drive head, operating mode and manufacturer’s conversion reference. A pressure figure on its own does not establish pile capacity.
Does Pile Logix pull readings from my torque logger?
No. Crews type torque and pressure readings into Pile Logix by hand as each pile goes in. Keep the logger's own export or screenshots alongside the report as supporting evidence.
What units should torque be in?
Nm or kNm are standard in Australia. Whichever you use, write it down and keep it consistent across the job.
How often should torque equipment be calibrated?
PN28 section 9.1 recommends calibration at least every six months. Confirm the schedule required by the manufacturer and project specification, including checks after damage or suspect readings. This guide does not set a universal interval for Australian projects.
Logging torque on site
If your crew still writes readings on paper, the free screw pile record sheet template covers torque and pressure columns. When you're ready to drop the clipboard, Pile Logix lets crews enter each reading on a phone or tablet and builds the screw pile installation report as a PDF.