Screw pile installation report, done on site
Every pile you log in Pile Logix goes straight into a clean installation report. When the last pile is in, download the PDF and email it to the engineer or certifier yourself.
What's in the report
The report header comes from the job and your business profile. You fill it in once and it's saved for next time.
- Your business header and logo at the top
- Customer and job address
- Install date and installers
- Pile specification, for example shaft size, wall thickness and helix size
- Auger torque spec for the drive head you used
- Optional installer notes for the engineer
Then there's one row for every pile:
| Column | What it records |
|---|---|
| Location no. | The pile number, matching the plan |
| Final depth | How deep the pile actually went |
| Expected depth | The design depth for that pile |
| 1st and 2nd extension | Extension lengths added, in metres |
| Cut length | How much was cut off the top |
| Machine PSI | The hydraulic pressure reading at final depth |
| Torque (Nm) | Installation torque |
| Predrill depth / comment | Predrilling, rock, refusal or anything else worth noting |

Why engineers and certifiers want it
The engineer signs off on what went in the ground. They want every pile accounted for, with depth and torque next to the design numbers so they can see at a glance whether each one hit spec. A handwritten sheet copied up at night is slow to check and easy to get wrong.
- Same layout every job. The engineer knows where to look.
- Design next to actual. Expected and final depth sit side by side for every pile.
- Logged on site. Readings go in as each pile goes in, not from memory at the end of the day.
- Ready when you finish. No typing it up. Download the PDF before you leave site.
Related guide: What engineers and certifiers check in a screw pile installation report
For measurement intervals, pressure-based estimates and supporting evidence, see how to record screw pile torque readings.
How you send it
Pile Logix gives you the PDF. You download it and email it to the engineer, certifier or builder yourself, the same way you'd send any other document. You stay in control of who gets it.
Not using software yet? Start with our free screw pile record sheet template, or see how the pile logging app works.