The engineer uses the installation report to decide whether the piles match the design, and the certifier often relies on that sign-off. A report with gaps can hold up the next stage of the job.

This guide covers what reviewers usually look for and why records get sent back. Requirements vary between projects, so confirm the specifics with the project engineer before piling starts.

Where the requirements come from

AS 2159 Piling: Design and installation

Most Australian projects reference AS 2159-2009 (incorporating Amendment No. 1), which sets minimum requirements for the design, construction and testing of piled footings, including steel screw piles. Section 7 covers materials and construction requirements, including tolerances and defects (Clause 7.2) and records of data (Clause 7.7). Project specifications often state that installation records must conform to Clause 7.7.

The drawings, geotechnical report and engineer's specification usually add detail, such as a target torque, minimum founding depth or position tolerance.

The New Zealand screw pile practice note

Practice Note 28, Screw Piles: Guidelines for Design, Construction and Installation (IPENZ, now Engineering New Zealand, 2015), is written for New Zealand and draws on AS 2159. It is a useful reference for what a screw pile record card should contain and how torque should be measured.

What goes in a screw pile installation report

Job and pile details

  • Project name, site address and client
  • Installation date and the installer or crew
  • Pile specification: shaft diameter, wall thickness, helix size and helix configuration
  • The design criteria you're working to, such as target torque or pressure and design depth

One record per pile

  • Pile ID and location. Matching the pile layout drawing.
  • Design depth and achieved depth. Side by side, so a short or deep pile stands out.
  • Extensions and cut-off. So installed length can be worked out.
  • Final installation torque. Recorded with units (Nm or kNm). Where torque is worked out from hydraulic pressure, record the pressure reading (PSI or bar) as well.
  • Notes. Predrilling depth, rock, refusal, obstructions, or anything that differed from the design.

Torque and capacity

Installation torque is widely used as an indicator of screw pile capacity. Practice Note 28 describes the empirical relationship as ultimate capacity = K × installation torque, where K varies with soil, pile size, helix configuration and installation, and says generic correlations should be validated with site-specific investigation and load testing.

So the engineer needs a torque value they can trust. Practice Note 28 recommends measuring over the last metre of installation or three helix diameters, whichever is greater. Some engineers also ask for torque or pressure readings over the full depth.

For the measurement method and evidence to keep, see our guide to recording screw pile torque readings.

Equipment and calibration

Record the drive head and machine used. Practice Note 28 recommends calibrating installation equipment and torque measuring devices at least every six months, and using the same drive head across a project where practical. Keep the current calibration certificate ready to send.

Position and inclination

Many specifications set tolerances for position and inclination (plumbness or rake). If yours does, record each pile's offset from design and inclination, or attach an as-installed survey.

Photos and sign-off

Photos of the torque readout at final depth and the completed record sheet are useful evidence. The report should end with the installer's sign-off.

Common reasons a report gets sent back

  1. Missing piles. The drawing shows 50 piles and the report lists 48. Abandoned or replaced piles need a row too.
  2. IDs that don't match the drawing. Piles numbered in install order can't be checked against a grid layout.
  3. No units. A torque of "8" means nothing without Nm or kNm.
  4. No design values. Achieved depth alone sends the reviewer back to the drawings for every pile.
  5. Short piles with no explanation. Note the reason and whether the engineer was contacted.
  6. Pressure with no conversion. If torque comes from hydraulic pressure, name the drive head used.
  7. No calibration evidence. An unverified reading puts the implied capacity in doubt.
  8. Records written up later. Identical readings typed up days afterwards raise questions.

Quick checklist before you send the report

  • Every pile on the layout drawing appears in the report
  • Pile IDs match the drawing
  • Design depth and achieved depth recorded for every pile
  • Final torque recorded with units, plus pressure reading where used
  • Pile spec recorded: shaft size, wall thickness, helix configuration
  • Extensions and cut-off lengths recorded
  • Notes for every pile that didn't go as designed
  • Drive head and machine identified, calibration certificate on file
  • Position and inclination recorded if the specification sets a tolerance
  • Installation date, installer and sign-off included

If you record on paper, the free screw pile record sheet template covers the core columns as a PDF, Excel (XLSX) or CSV file. Add any columns your engineer asks for.

How Pile Logix handles the report

Pile Logix is a field-records app for screw piling crews. The crew logs each pile on a phone or tablet as it goes in, and when the last pile is logged, the app builds a PDF screw pile installation report.

The report header carries your business details, the customer and job address, install date, installers, pile specification and the auger torque spec for the drive head used. Each pile gets a row with its location number, final depth beside expected depth, extensions, cut length, machine PSI, torque in Nm, and a predrill depth or comment column. You download the PDF and email it to the engineer or certifier yourself.

If a project also needs calibration certificates, photos, survey data or inclination records, send those alongside the report.

FAQ

What does AS 2159 require in pile installation records?

AS 2159-2009 covers records of data in Clause 7.7, and many project specifications require records to conform to it. Specifications and drawings usually add project-specific items, so confirm with the engineer before piling starts.

Why do engineers care so much about final installation torque?

Torque is used as an indicator of capacity through an empirical correlation. The engineer compares final torque with design torque to judge whether each pile will carry its load.

Can I record hydraulic pressure instead of torque?

Many crews read hydraulic pressure and convert it to torque for the drive head used. Record both values and the drive head so the engineer can check the conversion.

What should I do if a pile doesn't reach design depth?

Record the achieved depth and the reason, such as rock, refusal or torque reached early. Contact the engineer, who may need to approve the pile or ask for a change.

How often should torque equipment be calibrated?

Follow the project specification and manufacturer. Practice Note 28 recommends at least every six months.

Is a record sheet template enough for certification?

A template is a starting point. Engineers and certifiers can have their own requirements, so confirm which records they need before the job starts.

Need a cleaner report for your next job? See what goes into a Pile Logix installation report, or start with the free record sheet template.

Get your next report done on site

Start the 14-day free trial, no credit card needed, and download your first installation report on a real job.